Portland Square - 20th September 2001.
|
|
Building A:
The frame for Building A is progressing well - steelwork for the first two storeys is almost complete.
|
|
Buildings B and C:
Almost all of the precast concrete floor beams are in position on the first two floors of Buildings B and C. Work has now started on erecting the next two floors of steelwork for Building C.
|
|
Building C:
Although much of the lateral stiffness in each building is provided by a central shear frame there is other diagonal bracing to be found - here's a typical example of how the stiffness is being provided.
|
|
Site Visit:
The site was visited today by a group of our first year HND/BSc Civil Engineering students. The students were shown around the site by Armando - one of our MEng/BEng students who's working on the site during his optional Industrial Placement year.
|
|
|