Portland Square - 2nd October 2001.
|
|
Overview:
Here's a general view of the site, showing how construction on the three buildings is progressing. Erection of the next two floors of steel frame for Building C is progressing well; the cranes are being kept very busy indeed !. This picture was taken from the roof of the University's Davy Building.
|
|
Building A:
The first two floors of Building A have now been decked out with precast concrete floor units. The University's Sherwell Centre can be seen in the background.
|
|
|