Portland Square - 3rd August 2001
Cranes and Pile caps . |
Here's the first of the tower cranes - finished and ready for use.
|
Some of the piles bored on the site were more than 10m long. These four piles will eventually support one of the main structural elements.
|
The foundations are heavily reinforced - this photo shows the bottom steel for one of the pad foundations.
|
Holding-down bolts were cast into the foundations to fix the structural steel frame. The polystyrene 'cones' allow the bolt positions to be fine-tuned once the concrete has been cast.
|
![]() All structural concrete is cured under damp hessian until the formwork can be struck.
|
As part of the specification for the groundworks there was a requirement to test load one of the piles. The load was applied to the capped pile using a hydraulic jack - the reaction force was transferred to two adjacent piles by a steel spreader beam.
|
|
|