Introduction. I'll try to add new pictures to this web site at least once a week - the most recent pictures will be towards the top of the page. Simply click on a thumbnail image to get a better view. |
| 17th December 2001: Another 360 degree VR panoramic view - from the roof of Building B. |
| 12th November 2001: A 360 degree VR panoramic view of the inside of the Squash Courts. |
|
6th November 2001: Building C gets its plant room and atrium steel.
|
| 2nd November 2001: Building C ready for its plant room and atrium steel; roof finished on Squash Courts. |
| 30th October 2001: Progress; taking photographs. |
|
22nd October 2001: Now at roof level on all three buildings; finished floors.
|
|
12th October 2001: Steelwork reaches roof level for the first time.
|
| 10th October 2001: Mobile crane and portal frames. |
| 9th October 2001: Steel connections; retaining walls; precast stairs; Bovis staff. (Pictures not quite ready yet - here's a preview)
|
| 4th October 2001: A couple of 360 degree VR panoramic views. |
|
2nd October 2001: A quick update.
|
|
25th September 2001: More steel and concrete; painting in the Squash Courts.
|
|
20th September 2001: General progress; bracing; site visit.
|
| 18th / 19th September 2001: Squash Courts get a roof; work continues at speed on Buildings A, B and C. |
| 4th September 2001: More steelwork and floor beams; progress in the Squash Courts. |
| 31st August 2001: Shear frame for Building A is erected; Building C's first floor takes shape. |
| 28th / 30th August 2001: Steel for Building A arrives on site; work starts on the first floor for Building C. |
| 22nd August 2001: More steelwork - including the main shear frame for Building B; walls and a floor for the Squash Courts. |
| 16th August 2001: The first steelwork goes up on Building C; work progresses on the new Squash Courts. |
| 10th / 14th August 2001: The second tower crane is finished; the first steelwork arrives on site. |
|
8th August 2001: Almost ready for the steelwork; the second tower crane arrives. |
|
3rd August 2001: More foundations. |
|
31st July 2001: Erecting the first tower crane. |
|
27th July 2001: The first foundations are cast. |
|
13th July 2001: Construction begins. |